Create a Risk-Adjusted Schedule Based on Risk Inputs
Create a risk-adjusted schedule based on risk inputs.
To create a risk-adjusted schedule based on risk inputs, complete the following steps:
- Select the S3 // Risk tab.
- With the project selected in the Projects pane, in the Analysis group, click Build Scenario.
- Select Scenario Based on Risk Inputs, then select either PERT or Distribution Median.
- In the Analysis group, click Run Risk Analysis.